Financial Position as of May 31, 2008
Total funds received to date ......................................$3,034,257.00 - Praise God!!
Projected remaining pledges .......................................$309,770.00
Projected total cash ....................................................$3,344,027.00
Projected Cost
As of February 2008 ...................................................$3,700,000.00
Additional cost ................................................................$200,000.00
Total projected cost ....................................................$3,900,000.00
Additional cost items:
.............Audio Visual system changes
.............DP&L required Transformer
.............Weather delay costs
The Bottom Line
Projected total cash ....................................................$3,344,027.00
Total projected cost ....................................................$3,900,000.00
Projected gap to be bridged ........................................($555,973.00)
Our challenge is to bridge this gap by the end of 2009, so that Phase 1 is complete Debt Free